Toki Bridge Opening

Toki Bridge officially open!

Whakapono – Belief Tumanako – Hope Ko te aroha – Love The Toki Bridge opening day (29th March 2022) for the Toki Bridge was a joyous and fun experience for everyone concerned. Ngāti Waewae presented a beautiful piece of West Coast pounamu “gifted to the people of Buller” in recognition

Read more »
Wairoa Walkway Truss

Design of Wairoa Steel Truss works started…

Work started last week on the design of the Wairoa Clip-on Walkway Trusses. The concept was the winning solution as part of the successful Brian Perry Civil tender for the overall 175m long clip-on cycleway works for NZTA and Western Bay of Plenty District Council. The vibrant steel warren trusses

Read more »
Piling at Laurent Swale Footbridge

Laurent Swale Footbridge – bridge piling started!

This week marked a major milestone as bridge piling was completed for the Laurent Swale Footbridge in Cambridge (NZ). The footbridge construction is being led by Spartan Construction as part of the multi-million dollar Laurent Swale Project currently being constructed alongside Victoria Street. This vibrant but economic footbridge with wave-like

Read more »
Water of Leith Footbridge - Steel Mast and Steel Super Erected October 2018

Water of Leith Footbridge – steelwork mast erected!

The Water of Leith Bridge is taking shape on site! Last week the beautiful 22m high steel wish-bone mast was erected to accompany the 45m long steel superstructure bridging over the Water of Leith in Dunedin. Next stage is to add and stress the stay-cables and install decking and balustrades….

Read more »
Water of Leith Bridge Piling

Water of Leith Footbridge – driven piles installed!

Water of Leith Bridge Update: The works currently occurring on site are the installation of seven 18m long steel driven piles that will support the eastern end of the bridge and the 22m high steel mast. These driven piles are being installed by local piling firm McNeills and are being

Read more »
Water of Leith Bridge - DC Structures Studio

Water of Leith Footbridge – construction underway…

Exciting News! Construction for the Water of Leith Cyclebridge finally got underway last week. The Council, Construction Team, and Design Team met onsite on Tuesday 31st July to review and agree the survey set-out and the construction crew mobilized on Thursday 2nd August…. full steam ahead! Building Consent and Resource

Read more »
Hendon footbridge Concept 2011, Auckland

Hendon Park Footbridge Concept (2011)

This is the original footbridge concept for a 60m spanning architectural tied arch that was part of the winning tender for the Waterview Alliance back in 2011. Dan was the lead bridge engineer and bridge architect for the Hendon Park Footbridge whilst working at Beca when we were developing the initial tender designs